EXECUTIVE SUMMARY

INTRODUCTION

Objectives

Scope and Methodology

Background

FINDINGS AND RECOMMENDATIONS

I. PROJECTIONS

II. REPORTS

III. VALIDATION

IV. LAND BORDER PORTS' WORKLOAD ACCURACY

OTHER MATTERS

STATEMENT ON MANAGEMENT CONTROLS

APPENDIX I - Scope and Methodology

APPENDIX II - Background

APPENDIX III - Air Ports-of-Entry Output Reports

APPENDIX IV - Terms and Definitions

APPENDIX V - INS Comments on the Audit Recommendations

APPENDIX VI - Office of the Inspector General, Audit Division Analysis and Summary of Actions Taken to Close Report

 




EXECUTIVE SUMMARY

The Immigration and Naturalization Service (INS) has invested approximately $1.35 million and 5 years of effort to refine and implement a computer modeling program called the Workforce Analysis Model (WAM). The purpose of WAM was to develop an objective means to allocate staff at ports of entry. The purpose of our audit was to determine if WAM produces useful analyses and accurately identifies INS's workforce needs at ports of entry.

According to the Justice Management Division's budget staff, WAM's projections of staffing levels are beginning to be used by INS to support budget requests to Congress for additional positions. During the FY 1997 budget process, WAM's output was identified in budget documents that were used as support for the Attorney General's March 27, 1996, testimony before the House of Representatives Appropriations Subcommittee for the Department of Justice. In those documents, a "complex staffing model" (WAM) was mentioned as the support for the request of an additional 150 land border inspectors and 153 additional staff at airports.

To be useful, a computerized staffing model must accurately simulate the workload, consider the flow of the workload over time, match the available workforce against that workload, and accurately project and report the optimum number of staff needed and when they are needed. Although we believe the concept of computer modeling can be a useful and valuable analytical tool, WAM, at the time of our review, could not be relied upon to accurately determine the optimum number of inspectors needed at a port of entry (POE). The following is a summary of the findings, which are discussed in detail in the body of the report. Specifically, we found:

• There is no assurance that WAM will determine the optimum number of inspectors needed at a port of entry, because it only projects inspectors needed above the inspectors entered in the shift schedules. Further, WAM will not detect overstaffed work shifts or project staff decreases when needed.

• WAM output reports could present the data in a more useful format to assist Headquarters Inspections and port directors with managing and staffing their ports efficiently.

• Neither the inspection processing times, developed by the ports, nor WAM's output projections have been validated through a documented process.

• Vehicle and pedestrian counts at some land border ports were either estimated or had to be prorated to an hourly basis using a profile based upon judgment.

Prior to the release of this report, we provided a draft version to the INS and requested written comments on the recommendations. The INS agreed with all of our recommendations. (See Appendix V for the INS' Comments.) Based on those comments, the INS has taken adequate actions to close Recommendations 1 and 3. Actions to close Recommendations 2, 4, 5, 6, and 7 are still in process. Therefore, this report is resolved, but not closed.

#####